LPG Works at TATA HITACHI

Fawia successfully hands over LPG Pipeline Distribution works at Tata Hitachi. The work involved laying of new pipelines and tapping points. The new pipeline was to be connected with existing main LPG header. The Connection was an extremely sensitive job as it involved purging of existing header and hot works could be initiated only post successful purging of LPG from pipeline. The overall interconnection job took 3 days.